[4/8/19] Woodin Avenue Bridge Project Update

Posted in TransportationTagged , ,

Woodin Avenue Landing Park will be closed for the next two weeks (Monday, April 8, through Friday, April 19) due to heavy construction activities in the park.

Activities planned for the week of April 8th thru the 12th

  • Installing irrigation sleeves

  • Begin Landing Park wall

  • Concrete pours for curbs, planter seating, and sidewalks

  • Woodin Avenue Landing Park Closed

Activities planned for nest week Monday April 15th thru Friday April 19th –

  • Installation of bridge lamp posts

  • Finish Landing Park wall

  • Concrete pours for curbs, planter seating, and sidewalks

  • Landing Park closed

There are no bridge closures anticipated, only short stops in traffic to allow equipment and trucks in and out of the work areas. Pedestrian access continues to remain open at all times with bicyclists using the same area to cross. For safety, bicyclists are asked to walk their bikes due to the limited space and compromised condition of the roadway.

All aspects of the project are expected to be completed before Memorial Day Weekend, the end of May.

Note: This look reflects what the contractor currently anticipates. Weather and other circumstances can change construction crew activities and bridge access. Please visit WoodinAvenueBridgeProject.org for the most up-to-date information. 

The Woodin Avenue Bridge Project wraps together many efforts, including bridge restoration,safety improvements and upgrading utilities to accommodate future needs. The project also makes the area more inviting, widening 1,900 feet of sidewalks, adding 1,200 feet of new bike lanes, enhancing streetscapes, and adding the new Woodin Avenue Landing Park.